Construction of Waste Water Treatment Plant at Northeast (Mehmood Booti NE-I and Shadbagh NE-II) and South West (BABU SABU), Lahore

Project Introduction

Currently, no Wastewater Treatment Plant (WWTP) has been operating in Lahore and all the Wastewater is being discharged directly or indirectly into the River Ravi. At present, River Ravi is a sewage carrying drain and all the seepage from it, is nothing but sewage. Flow of sewage from the River Ravi is slowly polluting the ground water reservoir of Lahore and its vicinity. The project aims to address this grave environmental and health hazard by constructing wastewater treatment plants of 765 MGD capacity at Babu Sabu, Mahmood Boti and Shaadbagh area of Lahore.

Location

Lahore

Proposal Type

Unsolicited

Estimated Cost

PKR 51,621 million

Concession Period

25 years

Concerned/Sponsoring Agency

  • Housing Urban Development & Public Health Engineering Department (HUD&PHE) Department
  • Lahore Development Authority (LDA)
  • Water and Sanitation Agency (WASA), Lahore

Salient Features

  • Capacity: 765 MGD
  • Proposed treatment technology: Activated Sludge Processing (ASP)
  • End usage of treated water: To be trained into River Ravi and sale for irrigation purpose

Role of Government Agency

Provision of land and obtaining necessary NOCs and permissions

Role of Private Party

Design, Build, Finance, Operate, Maintain and Transfer Back to Government

Current Status

Project proposal under review. 

 