Lahore Ring Road Southern Loop (SL-III)

Introduction

Starts from Raiwind Road Interchange and ends at Proposed Interchange at Multan Road. The alignment passes through Pakistan Medical Society and Bahria Town and ends at Multan Road. A right of way (ROW) of 90 (ninety) meters has been adopted in general for the whole alignment of the project except at interchanges proposed at Pakistan Medical Society and Multan Road or in the areas where such ROW could not be maintained due to site/design constraints.

 

Location

Lahore

Proposal Type

Solicited with BOT

Estimated Cost

PKR 10448  million

Concession Period

25 Years

Concerned/Sponsoring Agency

Lahore Ring Road Authority (LRRA)/C&W Department

Current Status

  • Under achieving financial close  by Concessionaire (NLC)
  •  The concession agreement was signed between Government of Punjab and National Logistic Cell (NLC) on 13.06.2020
 

 

Salient Features

  • 8.00 Km (SL-III)
  • Interchanges= 02 Nos
  • Bridges other than interchanges= 03 Nos
  • Vehicular/Pedestrian Underpasses= 03 Nos
  • Drainage Culverts (0.9 m ø) = 14 Nos
  • Utility Pipe Culverts (2 in numbers of 1.2M dia)= Every 05 Km
  • Utility Pipes (2*225mm ø)= Every 2.50 Km
  • Intelligent Transport System

Role of Government Agency

  • Encumbrance free ROW
  • Land Acquisition
  • Relocation of Utilities

Role of Private Party

The Concessionaire shall be responsible for the overall implementation of the Project, including but not limited to the investigation, study, engineering, procurement, construction, financing and operation & maintenance of the Project in line with the terms and conditions provided in Concession Agreement.